Engineering Guide 05 · Fire & Life Safety

Pre-Order Checklist for Smoke Extraction (400/600 C) & EI Fire Dampers.

Five common specification mistakes that cause smoke control systems in Tashkent, Almaty and Astana to fail fire-authority acceptance tests on first inspection.

Thermal Rating400 C (2h) & 600 C (2h)
Cold Air TestMotor FLA checked at +20 C
Pressurization20 - 150 Pa egress door range
ActuatorsNO (Spring) vs NC (Reversible)

Critical Smoke-Control Audit Points

CHK-01

Verify Motor Power on Cold Commissioning Air (+20 C)

Fire acceptance tests run on +20 C ambient air, which is 2-3x denser than 400-600 C smoke.

  • Motors sized only for hot low-density gas trip circuit breakers during cold testing
  • Confirm motor kW and breaker sizing for +20 C start-up or specify VFD torque/current limiting
CHK-02

Match Damper Actuators Strictly (NO vs NC)

Mixing up fire dampers (NO) and smoke dampers (NC) is the most common procurement mistake.

  • Fire dampers (NO) must fail-safe closed on power loss via spring-return actuators
  • Smoke dampers (NC) open on fire command via reversible actuators matched to 24V or 230V fire panels

Pre-Procurement Verification Table

Check ItemWhat to VerifyRisk if MissedNekker Labs Verification
Smoke fan thermal class400 C / 120 min vs 600 C / 120 minFull rooftop fan replacement ordered by inspectorVerified against compartment fire load calculation
Roof curb & backdraft shutterInsulated vs uninsulated, roof pitchWater leaks and flange mismatch on roofSupplied as matched factory assembly (fan + curb + damper)

Smoke Control Audit & Supply

Certified AVZ and partner life-safety packages delivered across:

TashkentAlmatyAstanaSamarkandShymkentAtyrau

Smoke Control Questions

Can you audit our smoke-control fan and damper schedule before tender?

Yes. Email your schedule to info@nekkerlabs.com for a line-by-line review of thermal classes, actuators and duty points.

Technical sections & tools

Closer to manufacturer data.

Open the public Designer Workspace, browse engineering category guides or sign in to the project platform.

Let’s start with your project.

Email your HVAC equipment schedule, 3D/BIM pilot drawings or supply enquiry for engineering review.

Write an email
Projects and partnershipsinfo@nekkerlabs.com
Contacts
Rinat BaitemirProjects & Partnerships
+90 501 552 29 11
Alexandr KlimenkoKazakhstan · Almaty
+7 701 742 72 92
DIRECT PROJECT SUBMISSION

Attach drawings, equipment schedules, or BIM models

Upload PDF, DWG, RVT, IFC, Excel, or ZIP packages (up to 5 files, 100 MB total). Your submission creates an instant CRM dossier and alerts the regional desk.

Required scope
Project files or schedules (optional)
Drag and drop files here or click to browsePDF, XLSX, DWG, DXF, RVT, IFC, ZIP, PNG/JPG - up to 5 files, max 50 MB each / 100 MB batch
Offices & addresses
01 · Uzbekistan · Tashkent

OOO Nekker Labs

Uzbekistan, Tashkent, Yunusabad District, Bogishamol Street, 260A

Rinat Baitemirinfo@nekkerlabs.com
02 · Kazakhstan · Almaty

TOO Nekker

Kazakhstan, Almaty, Bostandyk District, Arkhat Microdistrict, Denis Ten Street, 2

Alexandr Klimenko+7 701 742 72 92
04 · USA · Wyoming

Nekker Labs

1309 Coffeen Avenue, STE 1200, Sheridan, Wyoming 82801